Green Line Extension (GLX)
A light rail train on the ramp to a viaduct in an urban area
A test train on the Red Bridge viaduct in January 2022
Overview
OwnerMassachusetts Bay Transportation Authority
LocaleCambridge, Somerville, and Medford, Massachusetts
Termini
  • Union Square (D)
  • Medford/​Tufts (E)
Stations7 open, 1 proposed
Service
TypeLight rail
SystemGreen Line (MBTA subway)
History
OpenedMarch 21, 2022 (Union Square Branch)
December 12, 2022 (Medford Branch)
Technical
Line length4.3 miles (6.9 km)
Number of tracks2
Track gauge4 ft 8+12 in (1,435 mm) standard gauge
ElectrificationOverhead line, 600 V DC[1]: 11.1-1 
Operating speed50 miles per hour (80 km/h)[1]: 1–5 
Route map

Legend
Green Line Extension
 Lowell Line 
Green Line Extension
Green Line Extension
Green Line Extension
Mystic Valley Parkway
proposed
Green Line Extension
Green Line Extension
Medford/​Tufts
Green Line Extension
Green Line Extension
Ball Square
Green Line Extension
Green Line Extension
Magoun Square
Green Line Extension
Green Line Extension
Gilman Square
Green Line Extension
Green Line Extension
East Somerville
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Union Square
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
 Fitchburg Line 
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Maintenance
Facility
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Lechmere
closed 2020
Green Line Extension
Green Line Extension
Green Line Extension
Green Line Extension
Lechmere
Green Line Extension
Green Line Extension
Green Line Extension
MBTA Commuter Rail to North Station
Green Line Extension
Green Line (MBTA) to Science Park

The Green Line Extension (GLX) was a construction project to extend the Massachusetts Bay Transportation Authority (MBTA) Green Line light rail system northwest into Somerville and Medford, two inner suburbs of Boston, Massachusetts. The project opened in two phases in 2022 at a total cost of $2.28 billion. Total ridership on the 4.3-mile (6.9 km) extension is estimated to reach 45,000 one-way trips per day in 2030.

The project begins at the north end of the Lechmere Viaduct, where the former ground-level Lechmere station was replaced by an elevated station on an extended viaduct. Two branches split north of Lechmere, with the Union Square Branch following the MBTA Commuter Rail Fitchburg Line right of way to Union Square station in Somerville. The Medford Branch follows the Lowell Line right-of-way to Medford/Tufts station with four intermediate stations. A new vehicle maintenance facility and storage yard is located in the Inner Belt District. The project includes a 1.9-mile (3.1 km) extension of the Somerville Community Path to North Point.

An extension of service beyond Lechmere was considered as early as 1922, with the first formal proposal in 1926. Despite appearing in other regional plans throughout the 20th century, the state did not commit to the project until 1990. Planning began in 2006 with a projected completion date of 2014; this was delayed to 2015, then to 2018. A groundbreaking was held in 2012, with several early construction elements over the next two years. The federal government committed $996 million of the $2.2 billion cost in 2014.

In 2015, with projected costs increased to $3.3 billion, the project was placed on hold. A revised plan, with more modest stations and other value engineering, was submitted in 2016 and approved in 2017. The main $1.08 billion design-build contract was issued in November 2017, with several optional items like platform canopies and a larger vehicle maintenance facility included. Construction began in 2018, with the old Lechmere station closed in May 2020. The new Lechmere station and Union Square Branch opened on March 21, 2022, while the Medford Branch opened on December 12, 2022. The Community Path extension opened in June 2023.

  1. ^ a b Cite error: The named reference techprov was invoked but never defined (see the help page).

and 17 Related for: Green Line Extension information

Request time (Page generated in 0.9042 seconds.)

Green Line Extension

Last Update:

The Green Line Extension (GLX) was a construction project to extend the Massachusetts Bay Transportation Authority (MBTA) Green Line light rail system...

Word Count : 11626

C Line Extension

Last Update:

C Line Extension is a project by the Los Angeles County Metropolitan Transportation Authority to extend the C Line (formerly known as the Green Line) from...

Word Count : 952

Green Line D branch

Last Update:

The Green Line D branch (also referred to as the Highland branch or Riverside Line) is a light rail line in Boston, Brookline, Cambridge, Newton, and Somerville...

Word Count : 4015

Somerville Community Path

Last Update:

rail line. Extensions opened in 1994 and 2015. A further 1.9-mile (3.1 km) extension to East Cambridge opened in June 2023 as part of the Green Line Extension...

Word Count : 967

Jubilee Line Extension

Last Update:

141°W / 51.509; -0.141 The Jubilee Line Extension (JLE) is the extension of the London Underground Jubilee line from Green Park to Stratford through south...

Word Count : 3341

Piccadilly line

Last Update:

Electric Railways of London (UERL) took over the line, it was renamed the Piccadilly line. Subsequent extensions were made to Cockfosters, Hounslow West and...

Word Count : 14926

Green Line E branch

Last Update:

the E branch was cut back to North Station for construction of the Green Line Extension, as part of which it was temporarily extended to Union Square in...

Word Count : 8619

Bakerloo line extension

Last Update:

The Bakerloo line extension is a proposed extension of the London Underground Bakerloo line in South London from its current terminus at Elephant & Castle...

Word Count : 7483

Silk Institute metro station

Last Update:

was inaugurated along with five other stations, as a part of the Green Line extension. There are 2 Entry/Exit points – A and B. Commuters can use either...

Word Count : 230

D Line Extension

Last Update:

The D Line Subway Extension Project, formerly known as the Westside Subway Extension, the Subway to the Sea, and the Purple Line Extension, is a construction...

Word Count : 5333

Karachi Breeze

Last Update:

of acquiring twenty-five 18-metre-long articulated buses for the Green Line Extension project. Lahore Metrobus Rawalpindi-Islamabad Metrobus Multan Metrobus...

Word Count : 1759

Lechmere station

Last Update:

opened on March 21, 2022, as part of the Green Line Extension (GLX). Lechmere station is served by Green Line D branch and E branch service. The first...

Word Count : 8974

Southwest LRT

Last Update:

The Southwest LRT (Metro Green Line Extension) is an under–construction 14.5-mile (23.3 km) light rail transit corridor in Hennepin County, Minnesota,...

Word Count : 2910

Luas

Last Update:

of the city and the green line has been extended north and south as a single line. Since the northern extension of the green line in 2017, the two lines...

Word Count : 8696

MBTA subway

Last Update:

Lechmere station, was closed in 2020 for construction of the Green Line Extension. The extension opened in two phases in 2022 with new branches from Lechmere...

Word Count : 2083

Jubilee line

Last Update:

with an extension to Stratford. The later stations are larger and have special safety features, both aspects being attempts to future-proof the line. Following...

Word Count : 4585

Northern line

Last Update:

London Transport. OCLC 23376254. Murphy, Simon (2005). Northern Line Extensions: Golders Green to Edgware, 1922–24. London: The History Press. ISBN 978-0-7524-3498-8...

Word Count : 8159

PDF Search Engine © AllGlobal.net