Citigroup building with a sketch of internal framework superimposed on one side. The same design is used on all four sides and transmits wind and gravity loads to the four support stilts. There is also a fifth support column in the center.

In July 1978, a possible structural flaw was discovered in Citicorp Center, a skyscraper that had recently been completed in New York City. Workers quietly made repairs over the next few months. The building, now known as Citigroup Center, occupied an entire block and was to be the headquarters of Citibank. Its structure, designed by William LeMessurier, had several unusual design features, including a raised base supported by four offset stilts and a column in the center, diagonal bracing which absorbed wind loads from upper stories, and a tuned mass damper with a 400-ton concrete weight floating on oil[1] to counteract oscillation movements. It was the first building that used active mechanical elements (the tuned mass damper) for stabilization.[1][2]

Concerned about "quartering winds" (wind directed diagonally toward the corners of the building rather than perpendicular to a wall) an undergraduate engineering student from Princeton University, Diane Hartley, investigated the structural integrity of the building and found it wanting. However, it is not clear whether her study ever came to the attention of LeMessurier, the chief structural engineer of the building.

At around the same time as Hartley was studying the question, according to a 2022 article by Lee DeCarolis, who in 1978 was a first-year architecture student at New Jersey Institute of Technology (NJIT), DeCarolis chose the building as the topic for a report assignment in his freshman class on the basic concepts of structural engineering. A professor Zoldos of NJIT expressed reservations to DeCarolis about the building's structure, and DeCarolis contacted LeMessurier, relaying what his professor had said. LeMessurier had also become aware that during the construction of the building, changes had been made to his design without his approval, and he reviewed the calculations of the building's stress parameters and the results of wind tunnel experiments.[2] He concluded there was a problem. Worried that a high wind could cause the building to collapse, LeMessurier directed that the building be reinforced.

The reinforcements were made stealthily at night while the offices in the building were open for regular operation during the day. The scenario of concern was for the integrity of the building structure was high wind conditions. Estimates at the time suggested that if the mass damper was disabled by a power failure, the building could be toppled by a wind of about 70-mile-per-hour (110 km/h) from a particular direction, with possibly many people killed as a result. The reinforcement effort was kept secret until 1995. The tuned mass damper has a major effect on the stability of the structure, so an emergency back-up generator was installed and extra staff was assigned to ensure that it would keep working reliably during the structural reinforcement.

The city had plans to evacuate the Citicorp building and other surrounding buildings if high winds did occur.[2] A hurricane did threaten New York during the retrofitting, but it changed course before arriving.

Ultimately, the retrofitting may not have been necessary. A NIST reassessment using modern technology later determined that the quartering wind loads were not the threat that LeMessurier and Hartley had thought. They recommended a reevaluation of the original building design to determine if the retrofitting had really been warranted.[3] It is not clear whether the NIST recommended reevaluation was ever conducted, although the question is only an academic one, since the reinforcement had been done.

  1. ^ a b Cite error: The named reference Online Ethics 1995 was invoked but never defined (see the help page).
  2. ^ a b c LeMessurier, William (November 17, 1995). "William LeMessurier-The Fifty-Nine-Story Crisis: A Lesson in Professional Behavior". MIT Mechanical Engineering Colloquium. National Academy of Engineering. Archived from the original on August 7, 2022. Retrieved August 7, 2022 – via YouTube. (tuned mass damper discussion starting at 14:08, reference to the building as the first and to LeMessurier as the "father of the tuned mass damper" at 25:50, phone call with student described at 28:34, finding out about bolt substitution 27:30 (when he learned of it 31:25), wind tunnel experiments 34:10, 16-year failure period if damper was not functioning 35:10, brief thought of suicide 38:15, insurance company interaction and conventionality of diagonal wind analysis 40:40 and 55:40, evacuation plan at 49:30)
  3. ^ Park, Sejun; Duthinh, Dat; Simiu, Emil; Yeo, DongHun (March 6, 2019). "Wind Effects on a Tall Building with Cross Section and Mid-size Base Columns: A Database-assisted Design Approach". Journal of Structural Engineering. 145 (5). New York. doi:10.1061/(asce)st.1943-541x.0002328. PMC 7909585. PMID 33642672. Archived from the original on August 7, 2022. Retrieved August 7, 2022.

and 12 Related for: Citicorp Center engineering crisis information

Request time (Page generated in 0.8316 seconds.)

Citicorp Center engineering crisis

Last Update:

In July 1978, a possible structural flaw was discovered in Citicorp Center, a skyscraper that had recently been completed in New York City. Workers quietly...

Word Count : 3784

Citigroup Center

Last Update:

The Citigroup Center (formerly Citicorp Center and also known by its address, 601 Lexington Avenue) is an office skyscraper in the Midtown Manhattan neighborhood...

Word Count : 12102

William LeMessurier

Last Update:

Building, and the Dallas Main Center. LeMessurier is perhaps best known for his role during the Citicorp Center engineering crisis, when he secretly reassessed...

Word Count : 573

Maruti Suzuki

Last Update:

currently available in 166 cities across India. Citicorp Maruti Finance Limited is a joint venture between Citicorp Finance India and Maruti Udyog Limited its...

Word Count : 6950

1970s

Last Update:

brought rare attention to the small South Asian country. Hugh Stubbins's Citicorp Center revolutionized the incorporation of solar panels in office buildings...

Word Count : 18185

Bank

Last Update:

Savings and Loan crisis in the 1980s and early 1990s, the Japanese banking crisis during the 1990s, and the sub-prime mortgage crisis in the 2000s. The...

Word Count : 7627

Rick Scott

Last Update:

Corporation, Charles Miller and Richard Ragsdale. With financing from Citicorp conditional on acquisition of HCA, the proposed holding company offered...

Word Count : 13589

Iranian Americans

Last Update:

the founder of Bratz, Isaac Larian. Hamid Biglari is vice-chairman of Citicorp. Bob Miner was the co-founder of Oracle Corporation and the producer of...

Word Count : 11972

List of largest mergers and acquisitions

Last Update:

September 2015. Retrieved 28 August 2015. Martin, Mitchell (7 April 1998). "Citicorp and Travelers Plan to Merge in Record $70 Billion Deal : A New No. 1:Financial...

Word Count : 11666

Oliver Wyman

Last Update:

firm had an influential client list, including corporations such as 3M, Citicorp, Procter & Gamble, The New York Times, and Xerox. It was acquired by Marsh...

Word Count : 7649

List of Eagle Scouts

Last Update:

Syria". Bryan on Scouting. "2006 Distinguished Engineering Graduate". Cockrell School of Engineering. "At largest-ever gathering of Eagle Scouts, Exxon...

Word Count : 7295

70 Pine Street

Last Update:

Retrieved March 31, 2020. Postal, Matthew A (December 6, 2016). "Citicorp Center" (PDF). New York City Landmarks Preservation Commission. p. 11. Archived...

Word Count : 11384

PDF Search Engine © AllGlobal.net